Solved question paper for CMA May-2017 (DIPLOMA civil enginerring 6th)

Construction management and accounts

Previous year question paper with solutions for Construction management and accounts May-2017

Our website provides solved previous year question paper for Construction management and accounts May-2017. Doing preparation from the previous year question paper helps you to get good marks in exams. From our CMA question paper bank, students can download solved previous year question paper. The solutions to these previous year question paper are very easy to understand.

These Questions are downloaded from www.brpaper.com You can also download previous years question papers of 10th and 12th (PSEB & CBSE), B-Tech, Diploma, BBA, BCA, MBA, MCA, M-Tech, PGDCA, B-Com, BSc-IT, MSC-IT.

Print this page

Question paper 1

  1. SECTION – A

    Q1. Fill in the blanks.

    a. Organizing is the __________ of a construction management.

    Answer:

  2. Read more
  3. b. Bar Chart is also known as __________ .

    Answer:

  4. c. DPC is laid to protect the building from __________.

    Answer:

  5. d. Accidents are ___________ on construction projects.

    Answer:

  6. e. After the project is properly planned, it is ___________

    Answer:

  7. f. Daily labour is paid on the basis of attendance marked on __________

    Answer:

  8. Read more
  9. g. Construction of residential building is an example of ___________

    Answer:

  10. Read more
  11. h. First stage in Construction is ___________.

    Answer:

  12. Read more
  13. i. Financial year is always closed on __________ every year.

    Answer:

  14. Read more
  15. j. Voucher is a written document kept in office record as a __________of payment

    Answer:

  16. Read more
  17. State true or false.

    k. An organization never has a common objective.

    Answer:

  18. l. Span control is not the principle of organization.

    Answer:

  19. m. Safety campaign helps in reducing the rate of accidents.

    Answer:

  20. n. Revised administrative approval is never sanctioned.

    Answer:

  21. o. Temporary advance can be recouped from time to time

    Answer:

  22. SECTION – B

    Q2. Attempt any Six questions.

    i. What are the resources of Construction Industry?

    Answer:

  23. Read more
  24. ii. What are the functions of owner in a construction team?

    Answer:

  25. Read more
  26. iii. Differentiate between PERT & CPM

    Answer:

  27. iv. What is the difference between Imprest & Temporary advance?

    Answer:

  28. Read more
  29. v. What is the need of safety measures?

    Answer:

  30. Read more
  31. vi. Enlist the important stages of inspection in construction work?

    Answer:

  32. Read more
  33. vii. What are the functions of trade union?

    Answer:

  34. Read more
  35. SECTION –C

    Attempt any three questions.

    Q3. What are the functions of construction management?

    Answer:

  36. Q4. What are the methods of scheduling? Explain them briefly

    Answer:

  37. Read more
  38. Q5. Explain the following:

    a) Activity b) Event C) Dummy Activity d) Critical Path

    Answer:

  39. Q6. What is the difference between stock & tool and plant accounts?

    Answer: