Solved question paper for SUR-1 Dec-2019 (DIPLOMA 3rd)
Solved Question Paper
Surveying-1 Dec-2019
PSBTE • DIPLOMA • Cvil Engineering • 3rd • Dec-2019
SUR-1 for Punjab State Board of Technical Education Diploma in Engineering is the subject page where students can find subject-wise previous year question papers for Surveying-1 in the 3rd semester of Civil Engineering. These old papers help with revision, repeated questions, and understanding the exam pattern before the exam. Use this page to practice with Civil Engineering semester papers, review commonly asked topics, and prepare more confidently. BRpaper is not the official website of the Punjab State Board of Technical Education or any university or board, but it helps students access previous year papers and exam preparation material in one place.
Solved Questions
Solved-
Least count of leveling staff is _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 Least Count of Leveling Staff is ________.
-
May 2018
Least count of leveling staff is ______.
-
-
Reciprocal ranging is also called _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
_____ is used to calculate the area of irregular figures.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2018
________ is used to calculate the area of irregular figures.
-
-
Plane table surveying is most suitable for preparing _____ maps.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 Plane table surveying is most suitable for preparing _____ maps.
-
May 2017
Plane table survey is suitable for ……………. scale mapping.
-
-
A 20 m chain is divided into _____ links.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2019 A 20m chain has _________links.
-
-
The last reading taken by dumpy level is _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 The last reading taken by dumpy level during levelling is _____ .
-
-
The bearing taken with respect to magnetic meridian is called _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
At Equator, the dip of the needle is _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
Mean sea level for India is _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
Levelling should always start from a _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2019 Leveling should always commence from a
-
Dec 2017
Leveling work should always commence from a---------------
-
Dec 2011 Leveling work should always commence from a ________.
-
May 2010 Leveling should always commence from a _______.
-
-
The reduced bearing of a line is S 20°W, the WCB will be _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
Open traverse is suitable in survey of _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
The principle of chain survey is to divide the area into network of _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 The principle of chain survey is to divide the area into network of _____.
-
Dec 2015 In Chain Surveying the area is divided in to a network of _________.
-
Dec 2005 The _______ of chain surveying is to divide the area into network of triangles.
-
-
In case of river, vision is free, but is obstructed _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2017
In case of river vision is free but ……………..is obstructed
-
May 2016 In case of river vision is free but ……………..is obstructed.
-
May 2010 In case of river vision is ______ but chaining is obstructed.
-
-
Optical square is used for setting out _____.Fill in the Blanks 1 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 Optical Square is used for setting _____.
-
-
Describe two point problems with neat sketch.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 Explain two point problems.
-
May 2022 Explain the Two Point Problem with neat sketch.
-
May 2020 Explain in detail two point problems.
-
May 2019 Explain two point problem.
-
Dec 2017
Explain in details two point problems
-
Dec 2015 Explain in details two point problem.
-
-
What do you understand by ranging? Explain different types of ranging.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2011 What do you mean by ranging? Explain indirect method of ranging.
-
-
Explain the sources of error in chaining and their prevention.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2021 What are the different types of errors in chaining? Explain it.
-
May 2008 What are the mistakes in chaining?
-
-
Explain true meridian, magnetic meridian and arbitrary meridian.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
May 2022 Explain true meridian, magnetic meridian and arbitrary meridian.
-
May 2021
Explain true, magnetic and assumed meridian.
-
Dec 2016 Write the difference between magnetic meridian and true meridian.
-
Dec 2005 What do you understand by magnetic and true meridian?
-
-
Explain line of collimation, bench mark and change point in levelling.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
Explain the term bearing and its type in details.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
Explain collimation method and rise fall method.Short Answer 5 Marks Dec-2019 • PSBTE DIPLOMA
-
The following staff readings were observed successively with a level, the instrument having been moved after 3rd, 6th and 8th reading 3.335, 2.610, 1.985, 3.090, 3.865, 2.270, 1.6605, 2.950, 2.040, 3.680. Calculate other RL’s if RL at BM = 523.35 m.Long Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
The following are the observed F.B and B.B of lines of closed traverse. Correct them where necessary for local attraction. Line AB 292°15’ / 111°45’, BC 221°45’ / 41°45’, CD 90°05’ / 270°, DE 80°35’ / 261°40’, EA 37°00’ / 216°30’.Long Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
The distance between two towns measured by a 20 m chain was 2000 m and when measured by 30 m chain was 8000 links. If 30 m chain was 1 link too short what correction was required in 20 m chain?Long Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
Convert the following WCB to reduced bearing: i) 75°30’Short Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2019 Convert the following WCB to reduced bearing: ii) 205°10’
-
Dec 2019 Convert the following reduced bearing to WCB: i) N25°20’W
-
Dec 2019 Convert the following reduced bearing to WCB: ii) S40°15’E
-
Dec 2016 Convert the following WCB to Reduced Bearing: 48°25’10”
-
Dec 2016 Convert the following WCB to Reduced Bearing: 200°20’10”
-
-
Convert the following WCB to reduced bearing: ii) 205°10’Short Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2019 Convert the following WCB to reduced bearing: i) 75°30’
-
Dec 2019 Convert the following reduced bearing to WCB: i) N25°20’W
-
Dec 2019 Convert the following reduced bearing to WCB: ii) S40°15’E
-
Dec 2016 Convert the following WCB to Reduced Bearing: 48°25’10”
-
Dec 2016 Convert the following WCB to Reduced Bearing: 200°20’10”
-
-
Convert the following reduced bearing to WCB: i) N25°20’WShort Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2019 Convert the following WCB to reduced bearing: i) 75°30’
-
Dec 2019 Convert the following WCB to reduced bearing: ii) 205°10’
-
Dec 2019 Convert the following reduced bearing to WCB: ii) S40°15’E
-
Dec 2016 Convert the following WCB to Reduced Bearing: 48°25’10”
-
Dec 2016 Convert the following WCB to Reduced Bearing: 200°20’10”
-
-
Convert the following reduced bearing to WCB: ii) S40°15’EShort Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
-
Dec 2019 Convert the following WCB to reduced bearing: i) 75°30’
-
Dec 2019 Convert the following WCB to reduced bearing: ii) 205°10’
-
Dec 2019 Convert the following reduced bearing to WCB: i) N25°20’W
-
Dec 2016 Convert the following WCB to Reduced Bearing: 48°25’10”
-
Dec 2016 Convert the following WCB to Reduced Bearing: 200°20’10”
-
-
A traverse is in the form of square (clockwise) ABCDA. If the bearing of line AB is 120°30’, find the bearings of other sides.Long Answer 10 Marks Dec-2019 • PSBTE DIPLOMA
Explore all data
FAQ
Frequently Asked Questions
Answers about this subject, solved papers, and preparation.
01 Where can I find SUR-1 Surveying-1 previous year question papers?
You can use this subject page to look for SUR-1 previous year question papers for PSBTE Diploma Civil Engineering 3rd semester.
02 Are these papers useful for revision before the exam?
Yes, old papers help you revise important topics, practice common question styles, and understand the exam pattern.
03 Does this page include solved papers?
This page is mainly for previous year question papers and exam preparation material. Solved papers may not be available for every paper.
04 Can I use these papers to check repeated questions?
Yes, previous year papers are useful for spotting repeated questions and commonly asked areas in Surveying-1.
05 Is BRpaper the official website of PSBTE?
No. BRpaper is not the official website of the Punjab State Board of Technical Education. It only helps students find previous year papers and related preparation content.