Solved question paper for CMA May-2016 (DIPLOMA 6th)
Solved Question Paper
Construction management and accounts May-2016
PSBTE • DIPLOMA • Cvil Engineering • 6th • May-2016
CMA in Punjab State Board of Technical Education Diploma in Engineering for Civil Engineering 6th Semester helps students find subject-wise previous year question papers and old papers for exam revision. Students can use these papers to understand the paper pattern, identify repeated questions, and prepare more confidently for the semester exam. This page is meant for quick access to CMA previous year question papers, question paper PDF references, and revision support for civil engineering semester 6. BRpaper is not the official website of the university or board, and the available papers are shared only for study and exam preparation reference.
Solved Questions
Solved-
Construction economy is __________ of Civil Engg Management.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
The project should be __________ with latest developed techniques economically.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
After the project is properly planned, it is ____________Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
May 2017
After the project is properly planned, it is ___________
-
-
Military organization is the___________ & the earliest form of organization.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
May 2019 Military organization is the ______ and the earliest form of organization.
-
May 2018
Military organization is the _______ and the earliest form of organization.
-
-
The job layout for any project will depend upon the _______measures.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
Operational analysis is used for ____________Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
The work of carrying out inspection should be ____________ in advance.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
The inspection __________ the life span of structure.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
Accidents are _____________ on construction projects.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
May 2018
Accidents are _______ on construction projects
-
May 2017
Accidents are ___________ on construction projects.
-
-
Persons working on the machinery should be __________ & mentally active.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
There are separate heads of accounts for receipts & ___________Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
A structurally sound proposal & detailed estimate is submitted for obtaining __________Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
The main disbursing officer in PWD system of accounting is ____________Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
Daily labour is paid on the basis of attendance marked on _____________Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
May 2018
Daily labour is paid on the basis of attendance marked on _______.
-
May 2017
Daily labour is paid on the basis of attendance marked on __________
-
Dec 2015 Daily labour is paid on the basis of attendance marked on ________.
-
-
The demand of goods from stock is presented in ____________ form.Fill in the Blanks 1 Marks May-2016 • PSBTE DIPLOMA
-
What are the functions of engineer in a Const. Team?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
Differentiate between PERT & CPM?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
May 2022 Write the difference between PERT & CPM.
-
May 2022 Explain PERT and CPM.
-
May 2021 Differentiate between PERT & CPM.
-
May 2021 Differentiate between PERT and CPM.
-
May 2020 Differentiate between PERT and CPM.
-
May 2019 Differentiate between PERT and CPM.
-
May 2018
Differentiate between PERT & CPM.
-
Dec 2018
Differentiate between PERT and CPM.
-
May 2017
Differentiate between PERT & CPM
-
Dec 2017
Differentiate between PERT & CPM.
-
Dec 2015 Differentiate between PERT and CPM.
-
May 2010 Differentiate between PERT and CPM.
-
May 2010 Differentiate between PERT and CPM.
-
May 2010 Give the importance of C.P.M. How it differs from PERT?
-
Dec 2009 Define and explain CPM or define and explain PERT.
-
-
What are the advantages of Functional Organization?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
May 2022 What are the advantages of functional organization?
-
May 2021 Explain functional organization. What are its advantages?
-
May 2019 Explain functional organization. What are its advantages?
-
May 2006 Give the merits and demerits of functional organisations.
-
May 2006 Give the merits and demerits of functional organisations.
-
May 2004 What do you understand by ‘Functional organisation’? Give its merits and demerits.
-
-
Enlist the important points to be kept in mind while placing of Equipments at construction site?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
Give advantages of Time Rate System?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
Dec 2015 Write down the advantages and disadvantages of time rate system.
-
-
What do you understand by 'Analysis of Progress'? Illustrate your answer briefly?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
May 2021 What do you understand by Analysis of progress?
-
-
What is the need for INSPECTION & QUALITY in building construction?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
May 2021 Enlist the important stages of inspection in construction work.
-
May 2020 What points will you keep in mind during inspection of building work?
-
May 2018
Enlist the important stages of inspection in construction work?
-
Dec 2018
What points you will keep in mind during inspection of building work
-
May 2017
Enlist the important stages of inspection in construction work?
-
Dec 2011 Explain principles of inspection in construction industry.
-
-
List any six Physiological causes responsible for accidents at construction site?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
May 2018
What are the causes of accidents on construction site?
-
May 2015 What are the various Psychological Causes of accidents on construction site ?
-
Dec 2011 What are the causes of accidents on construction sites?
-
Dec 2008 Define accident. What are the main causes of accidents on a construction site?
-
Dec 2008 Define accident. What are the main causes of accidents on a construction site?
-
-
Distinguish between Technical Sanction & Administrative Approval?Short Answer 5 Marks May-2016 • PSBTE DIPLOMA
-
May 2020 Distinguish between Technical Sanction and Administrative Approval.
-
Dec 2017
Differentiate between administrative approval and technical sanction?
-
Dec 2011 Distinguish between technical sanction and administrative approval.
-
Dec 2009 Differentiate between administrative approval and technical sanction.
-
-
Describe briefly the stages involved in a construction project?Long Answer 10 Marks May-2016 • PSBTE DIPLOMA
-
May 2022 Explain various stages in planning a construction project.
-
May 2021 Discuss the various stages in construction planning.
-
May 2021 Explain various stages in planning a construction project.
-
May 2020 Discuss the various stages in planning a construction project.
-
May 2019 Discuss the various stages in planning a construction project.
-
May 2015 Discuss the various stages in planning a construction project ?
-
-
What are the methods of scheduling? Explain them briefly?Long Answer 10 Marks May-2016 • PSBTE DIPLOMA
-
May 2017
What are the methods of scheduling? Explain them briefly
-
May 2010 Define scheduling. What are its advantages? Give the classification of schedules.
-
May 2010 Define scheduling. What are its advantages? Give the classification of schedules.
-
-
Discuss the important merits & demerits of three types of organization?Long Answer 10 Marks May-2016 • PSBTE DIPLOMA
-
May 2021 Discuss the important merits and demerits of three types of organization.
-
-
What are the principles of storing & stacking materials at site?Long Answer 10 Marks May-2016 • PSBTE DIPLOMA
-
May 2021 Explain the principle of storing and stacking materials at site.
-
May 2019 Explain the principle of storing and stacking materials at site.
-
Dec 2016 Explain the principle of storing and stacking materials at the site.
-
Dec 2011 What are the principles of storing and stacking materials at site?
-
May 2004 What are the principles of storing and stacking materials at site? Explain.
-
-
Explain Piece Rate System of wage payment & also give its advantages & disadvantages?Long Answer 10 Marks May-2016 • PSBTE DIPLOMA
-
May 2022 Explain time rate and piece rate system of wage payment with its advantages and disadvantages.
-
May 2010 Explain the advantages and disadvantages of timerate system of wage payment.
-
May 2010 Explain the advantages and disadvantages of piece rate system of wage payment.
-
May 2010 Explain the advantages and disadvantages of time rate system of wage payment.
-
May 2010 Explain the advantages and disadvantages of piece rate system of wage payment.
-
-
Explain duties of Junior Engineer?Short Answer 4 Marks May-2016 • PSBTE DIPLOMA
-
Dec 2016 Explain the duties of a junior engineer.
-
Dec 2015 Explain the duties of junior engineer.
-
Dec 2009 Write the duties of a JUNIOR ENGINEER.
-
Dec 2008 What are the duties of junior engineer?
-
Dec 2008 What are the duties of junior engineer?
-
May 2004 What are the duties of junior engineer?
-
-
Write down the instructions for preparing a muster roll?Short Answer 6 Marks May-2016 • PSBTE DIPLOMA
Explore all data
FAQ
Frequently Asked Questions
Answers about this subject, solved papers, and preparation.
01 Where can I find CMA previous year question papers for civil 6th semester?
You can use this page to access CMA previous year papers and related old question papers for Civil Engineering 6th semester revision.
02 Is this page only for Construction Management and Accounts?
Yes, this page is focused on CMA, the subject full name Construction Management and Accounts, for PSBTE Diploma in Civil Engineering 6th semester.
03 Can I use these papers to understand the exam pattern?
Yes, previous year papers help students understand question style, paper pattern, and commonly repeated topics before the exam.
04 Are these official papers from the board?
No, BRpaper is not the official website of the Punjab State Board of Technical Education. It only helps students find study and revision material.
05 Do you provide solved CMA question papers?
Solved papers may not always be available. This page is mainly for previous year papers and exam preparation reference.