Solved question paper for QSV Dec-2016 (DIPLOMA 6th)
Solved Question Paper
Quantity surveying and valuation Dec-2016
PSBTE • DIPLOMA • Cvil Engineering • 6th • Dec-2016
QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.
Solved Questions
Solved-
State the Units of Measurement of lime concrete.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Cement Plaster.
-
May 2022 State the unit of measurement for Cement Plaster.
-
May 2022 State the unit of measurement for Cement Plaster.
-
Dec 2017 State the units of measurement for cement concrete.
-
Dec 2015 State the units of measurements for cement concrete.
-
Dec 2015 State the units of measurements for cement plaster.
-
Dec 2015 Units of payment for cement concrete is ___________.
-
Dec 2008 Write the units of measurement and payment for precast cement concrete.
-
-
State the Units of Measurement of steel truss.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
State the Units of Measurement of doors and windows.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
Dec 2017 State the units of measurement for wood work in door frames.
-
May 2015 State the unit of measurement for Doors & Windows.
-
-
State the Units of Measurement of drain.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2017 State the unit of measurement for drain.
-
Dec 2015 State the units of measurements for drain.
-
-
State the Units of Measurement of welding.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2019 State the unit of measurement for Welding.
-
May 2017 State the unit of measurement for welding.
-
May 2007 Give the unit of measurement for welding.
-
-
State the Units of Measurement of D.P.C.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2019 State the unit of measurement for D.P.C.
-
Dec 2017 State the units of measurement for DPC.
-
May 2015 State the unit of measurement for D.P.C.
-
-
State the Units of Measurement of Snowcem.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
State the Units of Measurement of skirting.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Skirting.
-
May 2019 State the unit of measurement for Skirting.
-
-
State the Units of Measurement of brick work.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Brick work.
-
May 2022 State the unit of measurement for Brick Work.
-
May 2019 State the unit of measurement for Brick Work.
-
Dec 2017 State the units of measurement for brick work in foundation.
-
Dec 2017 State the units of measurement for ashlar masonry.
-
Dec 2015 State the units of measurements for brick work.
-
May 2007 Give the unit of measurement for honey comb brick work.
-
-
State the Units of Measurement of expansion joints.Very Short Answer 1.5 Marks Dec-2016 • PSBTE DIPLOMA
-
Dec 2008 Write the units of measurement and payment for expansion joint.
-
-
Find out the dry materials required for 10 sqm cement plaster 1:4 (1.25 cm thick).Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2020 Find out the Dry Materials required for 10 sq.m Cement Plaster 1:4 (1.25 cm thick).
-
Dec 2018
Find out the Dry Materials required for 10 sq.m Cement Plaster 1:4 (1.25 cm thick).
-
-
Describe in brief the various specifications of first class building.Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2018
Explain general specifications of first class building.
-
-
What do you mean by tools and plant? Give its comparison with stock.Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
Define tender and earnest money.Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2010 Define earnest money.
-
-
What is administrative approval? Why is it important while starting a project?Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
Write a note on piece work agreement.Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
What is valuation? Give the purpose of valuation.Short Answer 6 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 What is Valuation? Write down the purpose of Valuation.
-
May 2020 What is Valuation? Write down the purpose of Valuation.
-
May 2019 What is valuation? Give the purpose of valuation.
-
May 2018
Define valuation. Give the purpose of valuation
-
Dec 2018
What is Valuation? Write down the purpose of Valuation.
-
May 2017 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
May 2016 Write short note on Purpose of valuation.
-
May 2015 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
Dec 2015 What is valuation?
-
Dec 2015 Write down the purpose of valuation.
-
May 2010 Explain the purpose of valuation.
-
Dec 2008 Define valuation and explain purpose of valuation.
-
May 2007 What is the purpose of valuation?
-
-
Work out the analyses of rate for cement concrete 1:2:4 in slab. Labour for 10 cum cement concrete is 1 mason @ 450 Rs/day, 15 mazdoor @ 300 Rs/day, 2 bhisti @ 200 Rs/day. (Assume any other required data).Long Answer 10 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 Work out the analyses of rate for cement concrete 1:2:4 in slab. Labour for 10m³ cement concrete is 1 mason @ 450 Rs/day, 15 mazdoor @ 300 Rs/day, 2 Bhisti @ 200 Rs/day. Rate of material: cement bag Rs. 390/-, sand Rs. 850/- per m³. (Assume any missing data)
-
May 2020 Prepare the Analysis of Rate for 10 cu.m of Cement Concrete 1:2:4 from the following data: Labour for 10 cu.m Mason: 1 no. @ Rs. 300 per day; Labour: 15 no. @ Rs. 200 per day; Water Man: 2 no. @ Rs. 250 per day. Cost of Material Cement: Rs. 300 per Bag; Sand: Rs. 600 per cu.m; Bajri: Rs. 1200 per cu.m.
-
Dec 2018
Prepare the Analysis of Rate for 10 cu.m of Cement Concrete 1:2:4 from the following data:
\r\n\r\nLabour for 10 cu.m : Mason: 1 no. @Rs. 300 per day
\r\n\r\nLabour: 15 no. @Rs. 200 per day
\r\n\r\nWater Man: 2 no. @ Rs. 250 per day
\r\n\r\nCost of Material Cement: Rs. 300 per Bag
\r\n\r\nSand: Rs. 600 per cu.m
\r\n\r\nBajri: Rs. 1200 per cu.m.
-
May 2017 Work out the analyses of rates for cement concrete 1:4:8 in foundation. Labour for 10 cu.m cement concrete is 1 mason @ Rs. 450/- per day, 15 mazdoor @ Rs. 250/- per day, 2 bhisti @ Rs. 200/- per day. Rate of material: cement bag Rs. 300/-, sand Rs. 800/- per cu.m, coarse aggregate (bazri) Rs. 1000/- per cu.m.
-
May 2016 Prepare the analysis of rate for 10 cum of cement concrete 1:2:4 from the given data: labour for 10 cum; Mason = 1 @ Rs. 300 per day, Labour = 15 @ Rs. 200 per day, Water man = 2 @ Rs. 250 per day. Cost of material: Cement = Rs. 300 per bag, Sand = Rs. 600 per cum, Bajri = Rs. 1200 per cum.
-
May 2015 Work out the analysis of rates for cement concrete 1:4:8 in foundation. Labour for 10 cu.m cement concrete is 1 mason @ Rs. 500/- per day, 15 mazdor @ Rs. 300/- per day, 2 bhisti @ Rs. 250/- per day. Rate of material: cement bag Rs. 250/-, sand Rs. 600/- per cu.m, course aggregate (bazri) Rs. 1000/- per cu.m.
-
-
A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The N.S.L. are given below. If the formation level at Rd 0 is 75 meters, estimate the quantity of cutting for a formation width of 10 m. The side slope is 2:1 and there is no cross slope. Also find out the cost of cutting @450.00/cum.Long Answer 10 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL are given below: R.D (m) 0, 30, 60, 90, 120, 150; NSL (m) 70.50, 69.30, 71.40, 74.00, 75.10, 73.50. If the Formation Level at RD 0 is 65.00 metre, estimate the Quantity of Cutting for the Formation Width of 10 m. The Side Slope is 2:1 and there is no cross-slope. Also find out the Cost of Cutting @ Rs. 450 per cu.m.
-
May 2022 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The natural surface levels are given below: R.D. 0 30 60 90 120 150; N.S. level 71.4 70.7 72.6 74.05 75.4 74. If the formation level at Rd 0 is 72.5 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1 (Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.500.00 per m³.
-
May 2020 A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL are given below. If the Formation Level at RD 0 is 65.00 metre, estimate the quantity of cutting for the formation width of 10 m. The side slope is 2:1 and there is no cross-slope. Also find out the cost of cutting @ Rs. 450 per cu.m.
-
May 2018
A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30.The N.S levels are given below:
\r\n\r\n\r\n \r\n
\r\n\r\n\r\n \r\nRd \r\nN.S.(level) \r\n\r\n \r\n0 \r\n70.40 \r\n\r\n \r\n30 \r\n69.70 \r\n\r\n \r\n60 \r\n71.10 \r\n\r\n \r\n90 \r\n74.05 \r\n\r\n \r\n120 \r\n75.40 \r\n\r\n \r\n \r\n150 \r\n74.00 \r\nIf the formation level at Rd 0 is 65 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1(Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.450.00 cu m.
-
Dec 2018
SECTION-C
Attempt any three Questions. 10x3=30 Q4. A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL is given below:
R.D(m) NSL(m) 0 70.50 30 69.30 60 71.40 90 74.00 120 75.10 150 76.10 If the Formation Level at RD 0 is 75.00 metre, Estimate the Quantity of Cutting for the Formation Width of 10 m. The Side Slope is 2:1 and there is no cross-slope. Also find out the Cost of Cutting @ Rs. 450 % cu.m.
-
Dec 2015 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The N.S. levels are given below: RD 0 = 70.50, 30 = 69.30, 60 = 71.40, 90 = 74.00, 120 = 75.10, 150 = 73.50. If the formation level at 0 is 65 m, estimate the quantity of cutting for a formation width of 10 metres. The side slope is 2:1 (Horizontal: Vertical) and there is no cross slope. Also find the cost of cutting @ Rs. 450 per cum.
-
-
Define sinking fund.Very Short Answer 2 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 Explain Sinking Fund.
-
-
Define scrap value.Very Short Answer 2 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 Define Salvage Value.
-
May 2022 Explain Scrap Value.
-
May 2010 Discuss scrap value.
-
-
Define capital cost.Very Short Answer 2 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 Explain Capital Cost.
-
-
Define gross income.Very Short Answer 2 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 Explain Gross Income.
-
-
Define year purchase.Very Short Answer 2 Marks Dec-2016 • PSBTE DIPLOMA
-
May 2022 Explain Year Purchase.
-
-
Work out the quantities of excavation for foundation from the given drawing.Long Answer Dec-2016 • PSBTE DIPLOMA
-
May 2022 Work out the Quantities of Excavation for Foundation from the given Drawing (Wall thickness-0.30 m all around).
-
May 2017 Work out the quantity of excavation for foundation from the given drawing.
-
May 2016 Calculate the quantities of excavation for foundation from the sketch attached.
-
May 2015 Work out the quantity of excavation for foundation from the given drawing.
-
-
Work out the quantities of cement concrete 1:6:18 in foundation from the given drawing.Long Answer Dec-2016 • PSBTE DIPLOMA
-
May 2022 Work out the Quantities of P.C.C in Foundation (1:6:18) from the given Drawing (Wall thickness-0.30 m all around).
-
May 2017 Work out the quantity of cement concrete 1:6:18 in foundation from the given drawing.
-
May 2015 Work out the quantity of cement concrete 1:6:18 in foundation from the given drawing.
-
-
Work out the quantities of brick masonry in foundation and plinth from the given drawing.Long Answer Dec-2016 • PSBTE DIPLOMA
-
May 2022 Work out the Quantities of Mud Masonry in Foundation and Plinth from the given Drawing (Wall thickness-0.30 m all around).
-
May 2017 Work out the quantity of mud masonry in foundation and plinth from the given drawing.
-
May 2015 Work out the quantity of mud masonry in foundation and plinth from the given drawing.
-
Dec 2008 Work out the quantities of excavation for foundation for a room as shown in Figure 1.
-
Dec 2008 Work out the quantities of lime concrete in foundation for a room as shown in Figure 1.
-
Dec 2008 Work out the quantities of mud masonry in foundation and plinth for a room as shown in Figure 1.
-
Dec 2008 Work out the quantities of mud masonry in super structure for a room as shown in Figure 1.
-
May 2007 Work out quantities of excavation for foundation for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
May 2007 Work out quantities of CC in foundation for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
May 2007 Work out quantities of brick work in foundation and plinth in cement mortar for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
May 2007 Work out quantities of brick work in super structure in cement mortar for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
Explore all data
FAQ
Frequently Asked Questions
Answers about this subject, solved papers, and preparation.
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?
You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.
02 Is this page for Quantity Surveying and Valuation only?
Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.
03 Can I use these papers for revision before exams?
Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.
04 Are these official question papers from PSBTE?
No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.
05 Do you provide solved QSV question papers?
Some question papers may be available for practice, but this page does not guarantee solved papers for every year.