Solved question paper for QSV May-2015 (DIPLOMA 6th)

Solved Question Paper

Quantity surveying and valuation May-2015

PSBTE • DIPLOMA • Cvil Engineering • 6th • May-2015

QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.

Solved Questions

Solved
  1. Number of bricks required for 1 cu.m brick masonry is _________.
    Fill in the Blanks 1 Marks May-2015 • PSBTE DIPLOMA
  2. Capitalized value = net annual rent × _________.
    Fill in the Blanks 1 Marks May-2015 • PSBTE DIPLOMA
  3. An agreement which is enforceable by law is a _________.
    Fill in the Blanks 1 Marks May-2015 • PSBTE DIPLOMA
  4. A reasonable profit usually ________% for contractor is included in the analysis of rates.
    Fill in the Blanks 1 Marks May-2015 • PSBTE DIPLOMA
  5. Dry material required for 1 cu.m cement concrete is _________ cu.m.
    Fill in the Blanks 1 Marks May-2015 • PSBTE DIPLOMA
  6. State the unit of measurement for Earthwork.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  7. State the unit of measurement for Steelwork.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  8. State the unit of measurement for Painting.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  9. State the unit of measurement for D.P.C.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  10. State the unit of measurement for Drip course.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  11. State the unit of measurement for Doors & Windows.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  12. State the unit of measurement for Electricity Fitting.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  13. State the unit of measurement for Bitumen Road Surfacing.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  14. State the unit of measurement for Water Closet.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  15. State the unit of measurement for Glass Panes.
    Short Answer 1 Marks May-2015 • PSBTE DIPLOMA
  16. Define an estimate. Give its importance or objectives. Name the various types of estimate.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  17. Write a note on analysis of rates.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  18. Find out the dry material for 100 cu.m brick masonry in cement sand mortar 1:5.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  19. Find out the dry material required for 100 cu.m cement concrete 1:2:4.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  20. Explain the principles of valuation.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  21. Define contractor. What are the essential qualifications of a contractor?
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  22. Distinguish clearly between preliminary estimate and detailed estimate.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  23. Write a short note on depreciation of buildings.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  24. Differentiate between security deposit and retention money.
    Long Answer 5 Marks May-2015 • PSBTE DIPLOMA
  25. Prepare a preliminary estimate of a building having plinth area equal to 1600 sq.m. Given that plinth area rate is Rs. 2000/- per sq.m; extra for architectural work is 1.5% of the building cost; extra for electrical installation (10%) plus water supply and sanitary installations (6%) = 16% of the building cost; extra for other services is 8% of the building cost; contingencies and supervision charges are 10%.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  26. Work out the analysis of rates for cement concrete 1:4:8 in foundation. Labour for 10 cu.m cement concrete is 1 mason @ Rs. 500/- per day, 15 mazdor @ Rs. 300/- per day, 2 bhisti @ Rs. 250/- per day. Rate of material: cement bag Rs. 250/-, sand Rs. 600/- per cu.m, course aggregate (bazri) Rs. 1000/- per cu.m.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  27. Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  28. What is contract? Explain the different types of contract.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  29. Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following data: Rd 0 = 205.00, Rd 30 = 205.00, Rd 60 = 206.00, Rd 90 = 206.00, filling or banking level = 210.00. The formation is in a downward gradient of 1 in 30. Formation width is 10 meters and side slope is 2:1 (Horizontal:Vertical). Rate of earthwork is Rs. 400.00 per cu.m.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  30. Work out the quantity of excavation for foundation from the given drawing.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  31. Work out the quantity of cement concrete 1:6:18 in foundation from the given drawing.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  32. Work out the quantity of mud masonry in foundation and plinth from the given drawing.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA
  33. Work out the quantity of mud masonry in super structure from the given drawing.
    Long Answer 10 Marks May-2015 • PSBTE DIPLOMA

Explore all data

FAQ

Frequently Asked Questions

Answers about this subject, solved papers, and preparation.

Updated regularly
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?

You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.

02 Is this page for Quantity Surveying and Valuation only?

Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.

03 Can I use these papers for revision before exams?

Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.

04 Are these official question papers from PSBTE?

No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.

05 Do you provide solved QSV question papers?

Some question papers may be available for practice, but this page does not guarantee solved papers for every year.