Solved question paper for QSV May-2017 (DIPLOMA 6th)

Solved Question Paper

Quantity surveying and valuation May-2017

PSBTE • DIPLOMA • Cvil Engineering • 6th • May-2017

QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.

Solved Questions

Solved
  1. The attendance of the laborers is recorded daily in __________.
    Fill in the Blanks 1 Marks May-2017 • PSBTE DIPLOMA
  2. The loss in the value of the property due to structural deterioration is called __________.
    Fill in the Blanks 1 Marks May-2017 • PSBTE DIPLOMA
  3. The amount submitted by contractor as a guarantee of tender is called __________.
    Fill in the Blanks 1 Marks May-2017 • PSBTE DIPLOMA
  4. Number of bricks required for 1 cu.m brick masonry is __________.
    Fill in the Blanks 1 Marks May-2017 • PSBTE DIPLOMA
  5. One bag of cement = __________ kg.
    Fill in the Blanks 1 Marks May-2017 • PSBTE DIPLOMA
  6. State the unit of measurement for white washing.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  7. State the unit of measurement for wash basin (size specified).
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  8. State the unit of measurement for dado.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  9. State the unit of measurement for welding.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  10. State the unit of measurement for half brick wall.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  11. State the unit of measurement for flooring.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  12. State the unit of measurement for drain.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  13. State the unit of measurement for steel work.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  14. State the unit of measurement for glass panes.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  15. State the unit of measurement for supply of timber.
    Short Answer 1 Marks May-2017 • PSBTE DIPLOMA
  16. Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
    Short Answer 5 Marks May-2017 • PSBTE DIPLOMA
  17. Define an estimate. Give its importance or objectives. Name the various types of estimate.
    Long Answer 5 Marks May-2017 • PSBTE DIPLOMA
  18. Write a note on analyses of rates.
    Short Answer 5 Marks May-2017 • PSBTE DIPLOMA
  19. Find out the dry material required for 1 cu.m cement concrete 1:2:4.
    Short Answer 5 Marks May-2017 • PSBTE DIPLOMA
  20. What do you mean by tender?
    Short Answer 5 Marks May-2017 • PSBTE DIPLOMA
  21. Distinguish clearly between preliminary estimate and detailed estimate.
    Long Answer 5 Marks May-2017 • PSBTE DIPLOMA
  22. Explain the principles of valuation.
    Long Answer 5 Marks May-2017 • PSBTE DIPLOMA
  23. Define contractor. What are essential qualifications of a contractor?
    Long Answer 5 Marks May-2017 • PSBTE DIPLOMA
  24. Write a short note on depreciation of buildings.
    Short Answer 5 Marks May-2017 • PSBTE DIPLOMA
  25. Prepare a preliminary estimate of a building having plinth area equal to 2000 sq.m. Given that plinth area rate is Rs. 2100/- per sq. m; extra for architectural work is 1.5% of the building cost; extra for electrical installation (10%) and water supply and sanitary installations (6%) = 16% of the building cost; extra for other services is 8% of the building cost; contingencies and supervision charges are 10%.
    Long Answer 10 Marks May-2017 • PSBTE DIPLOMA
  26. Work out the analyses of rates for cement concrete 1:4:8 in foundation. Labour for 10 cu.m cement concrete is 1 mason @ Rs. 450/- per day, 15 mazdoor @ Rs. 250/- per day, 2 bhisti @ Rs. 200/- per day. Rate of material: cement bag Rs. 300/-, sand Rs. 800/- per cu.m, coarse aggregate (bazri) Rs. 1000/- per cu.m.
    Long Answer 10 Marks May-2017 • PSBTE DIPLOMA
  27. Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
    Long Answer 10 Marks May-2017 • PSBTE DIPLOMA
  28. What is contract? Explain the different type of contract.
    Long Answer 10 Marks May-2017 • PSBTE DIPLOMA
  29. Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following data: Rd 0, 30, 60, 90; N.S. levels 205.00, 205.60, 206.10, 206.90; formation in a downward gradient of 1 in 30; formation width 10 meters; side slope 2:1 (horizontal: vertical); rate of earthwork Rs. 425.00 per cu.m.
    Long Answer 10 Marks May-2017 • PSBTE DIPLOMA
  30. Work out the quantity of excavation for foundation from the given drawing.
    Comprehension 10 Marks May-2017 • PSBTE DIPLOMA
  31. Work out the quantity of cement concrete 1:6:18 in foundation from the given drawing.
    Comprehension 10 Marks May-2017 • PSBTE DIPLOMA
  32. Work out the quantity of mud masonry in foundation and plinth from the given drawing.
    Comprehension 10 Marks May-2017 • PSBTE DIPLOMA
  33. Work out the quantity of mud masonry in super structure from the given drawing.
    Comprehension 10 Marks May-2017 • PSBTE DIPLOMA

Explore all data

FAQ

Frequently Asked Questions

Answers about this subject, solved papers, and preparation.

Updated regularly
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?

You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.

02 Is this page for Quantity Surveying and Valuation only?

Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.

03 Can I use these papers for revision before exams?

Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.

04 Are these official question papers from PSBTE?

No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.

05 Do you provide solved QSV question papers?

Some question papers may be available for practice, but this page does not guarantee solved papers for every year.