Solved question paper for QSV May-2018 (DIPLOMA 6th)

Solved Question Paper

Quantity surveying and valuation May-2018

PSBTE • DIPLOMA • Cvil Engineering • 6th • May-2018

QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.

Solved Questions

Solved
  1. SECTION-A

    Q1. a) Fill in the blanks.

    i. The value of a property building after its working tenure without being dismantled is known as …………

    Very Short Answer 15x1=15 Marks May-2018 • PSBTE DIPLOMA
  2. While analyzing the rates, contractor profit is added at the rate of………………%.

    Very Short Answer May-2018 • PSBTE DIPLOMA
  3. The attendance of the laborers is recorded daily in…………………..

    Very Short Answer May-2018 • PSBTE DIPLOMA
  4. In the analysis of rate the number of bricks taken into account per cubic meter is……………...

    Very Short Answer May-2018 • PSBTE DIPLOMA
  5. State the unit of measurement for the following:-

    vi. Electric Fitting xi. D.P.C

    Short Answer May-2018 • PSBTE DIPLOMA
  6. Cement Plaster

    Very Short Answer May-2018 • PSBTE DIPLOMA
  7. Steel doors and Windows

    Very Short Answer May-2018 • PSBTE DIPLOMA
  8. Supply of Bitumen/tar

    Very Short Answer May-2018 • PSBTE DIPLOMA
  9. Supply of water closet(size specified)

    Very Short Answer May-2018 • PSBTE DIPLOMA
  10. Supply of varnish, oil

    Very Short Answer May-2018 • PSBTE DIPLOMA
  11. Rain Water pipe

    Very Short Answer May-2018 • PSBTE DIPLOMA
  12. Supply of bricks

    Short Answer May-2018 • PSBTE DIPLOMA
  13. Distempering

    Very Short Answer May-2018 • PSBTE DIPLOMA
  14. SECTION-B

    Q2. Attempt any six questions.

    a. What are the various duties of quantity surveyor?

    Short Answer 6x5=30 Marks May-2018 • PSBTE DIPLOMA
  15. What do you understand by estimate? Give the importance of estimate.

    Short Answer May-2018 • PSBTE DIPLOMA
  16. What are the factors affecting the Analysis of rates

    Short Answer May-2018 • PSBTE DIPLOMA
  17. Find out the dry material required for 1cu.m cement concrete 1:4:8

    Short Answer May-2018 • PSBTE DIPLOMA
  18. Find out the dry material for 1cu.m brick masonry in cement sand mortar 1:4.

    Short Answer May-2018 • PSBTE DIPLOMA
  19. Define valuation. Give the purpose of valuation

    Short Answer May-2018 • PSBTE DIPLOMA
  20. Calculate the value of year’s purchase whose life is 20 years and the rate of interest is 6%.For sinking fund rate of interest is 5%

    Short Answer May-2018 • PSBTE DIPLOMA
  21. Write a short note on scrap value, book value and outgoings.

    Short Answer May-2018 • PSBTE DIPLOMA
  22. Define Contract? What are the essential elements of contracts?

    Short Answer May-2018 • PSBTE DIPLOMA
  23. SECTION-C

    Attempt any three questions.

    Q3. A RCC simply supported beam with following data

    Clear Span=3.5m

    Bearing on Wall=200mm

    Thickness of wall=300mm

    Size of the beam=300mmX500mm

    Main Reinforcement=5-20mm ɸ HYSD bars

    (Three Bars up at l/7 from the inner face of support)

    Stirrups=8mm ɸ 2 legged @ 200mm c/c.

    Anchor Bars=2-12 ɸ mm

    Calculate the total quantity of mild steel reinforcement also prepare the bar bending schedule

    Long Answer 3x10=30 Marks May-2018 • PSBTE DIPLOMA
  24. Workout the analyses of rates for brick masonry cement mortars 1:4 in superstructure. Labour for 10cu.m brick masonry 8 brick layer @ Rs. 500/- per day, 15 mazdor @ Rs. 300/- , 2 Bhisti @ Rs. 250/- per day. Rate of material: - cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks 4000/- per thousand.

    Long Answer May-2018 • PSBTE DIPLOMA
  25. Explain general specifications of first class building.

    Long Answer May-2018 • PSBTE DIPLOMA
  26. A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30.The N.S levels are given below: 

    Rd N.S.(level)
    0 70.40
    30 69.70
    60 71.10
    90 74.05
    120 75.40
    150 74.00

    If the formation level at Rd 0 is 65 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1(Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.450.00 cu m.

    Long Answer May-2018 • PSBTE DIPLOMA

Explore all data

FAQ

Frequently Asked Questions

Answers about this subject, solved papers, and preparation.

Updated regularly
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?

You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.

02 Is this page for Quantity Surveying and Valuation only?

Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.

03 Can I use these papers for revision before exams?

Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.

04 Are these official question papers from PSBTE?

No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.

05 Do you provide solved QSV question papers?

Some question papers may be available for practice, but this page does not guarantee solved papers for every year.