QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.
Solved Questions
Solved-
Number of bricks required for 1 Cu.m brick masonry is ______.Fill in the Blanks 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 How many bricks are required for 1 cu.m Brick Masonry?
-
Dec 2018
Fill in the blanks.
\r\n\r\ni. No. of bricks for 1 cu.m Brick Masonry is ________.
-
May 2017 Number of bricks required for 1 cu.m brick masonry is __________.
-
Dec 2017 No. of bricks in 1 cum of brick masonry is __________
-
May 2015 Number of bricks required for 1 cu.m brick masonry is _________.
-
Dec 2015 Number of bricks required for 1 cum. brick masonry is __________.
-
-
Capitalized value = net annual rent × _______.Fill in the Blanks 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Capitalized value = net annual rent × Year’s Purchase
-
May 2015 Capitalized value = net annual rent × _________.
-
-
On acceptance of the tender ____ % of the tendered amount has to be paid as security money.Fill in the Blanks 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 On acceptance of the tender 20% of the tendered amount must be paid as security money.
-
-
A reasonable profit usually ____ % for contractor is included in the analysis of rates.Fill in the Blanks 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 A reasonable profit usually 15% for contractor is included in the analysis of rates.
-
May 2018
While analyzing the rates, contractor profit is added at the rate of………………%.
-
May 2015 A reasonable profit usually ________% for contractor is included in the analysis of rates.
-
-
Total dry material required for 1 cu.m cement concrete is _____ cu.m.Fill in the Blanks 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 How much quantity of dry mortar is required for 1 cu.m of Cement Concrete?
-
May 2022 Total Dry material required for 1m³ cement concrete is ________ m³.
-
Dec 2017 Dry material required for 1 cum of cement concrete is __________ cum
-
Dec 2015 Dry mortar required for 1 cum cement concrete is __________.
-
-
State the unit of measurement for Earthwork.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Earthwork.
-
Dec 2017 State the units of measurement for earthwork.
-
May 2016 State the units of measurements and payment for Earthwork.
-
May 2015 State the unit of measurement for Earthwork.
-
Dec 2015 State the units of measurements for earth work.
-
-
State the unit of measurement for Flooring.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Flooring.
-
May 2017 State the unit of measurement for flooring.
-
Dec 2017 State the units of measurement for concrete flooring.
-
May 2016 State the units of measurements and payment for Flooring.
-
Dec 2015 State the units of measurements for flooring.
-
-
State the unit of measurement for Distempering.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
State the unit of measurement for D.P.C.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
Dec 2017 State the units of measurement for DPC.
-
Dec 2016 State the Units of Measurement of D.P.C.
-
May 2015 State the unit of measurement for D.P.C.
-
-
State the unit of measurement for Steel work.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 State the unit of measurement for Steel work.
-
May 2017 State the unit of measurement for steel work.
-
May 2016 State the units of measurements and payment for Steel.
-
May 2015 State the unit of measurement for Steelwork.
-
Dec 2015 State the units of measurements for steel work.
-
May 2007 Give the unit of measurement for steel work.
-
-
State the unit of measurement for Brick Work.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Brick work.
-
May 2022 State the unit of measurement for Brick Work.
-
Dec 2017 State the units of measurement for brick work in foundation.
-
Dec 2017 State the units of measurement for ashlar masonry.
-
Dec 2016 State the Units of Measurement of brick work.
-
Dec 2015 State the units of measurements for brick work.
-
May 2007 Give the unit of measurement for honey comb brick work.
-
-
State the unit of measurement for Electric Fitting.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2018
State the unit of measurement for the following:-
\r\n\r\nvi. Electric Fitting xi. D.P.C
-
May 2015 State the unit of measurement for Electricity Fitting.
-
-
State the unit of measurement for Welding.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2017 State the unit of measurement for welding.
-
Dec 2016 State the Units of Measurement of welding.
-
May 2007 Give the unit of measurement for welding.
-
-
State the unit of measurement for Skirting.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 State the Units of Measurement for Skirting.
-
Dec 2016 State the Units of Measurement of skirting.
-
-
State the unit of measurement for R.C.C. slab roofing.Very Short Answer 1 Marks May-2019 • PSBTE DIPLOMA
-
Dec 2008 Write the units of measurement and payment for R.C.C. slab roofing.
-
-
What is valuation? Give the purpose of valuation.Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 What is Valuation? Write down the purpose of Valuation.
-
May 2020 What is Valuation? Write down the purpose of Valuation.
-
May 2018
Define valuation. Give the purpose of valuation
-
Dec 2018
What is Valuation? Write down the purpose of Valuation.
-
May 2017 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
May 2016 Write short note on Purpose of valuation.
-
Dec 2016 What is valuation? Give the purpose of valuation.
-
May 2015 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
Dec 2015 What is valuation?
-
Dec 2015 Write down the purpose of valuation.
-
May 2010 Explain the purpose of valuation.
-
Dec 2008 Define valuation and explain purpose of valuation.
-
May 2007 What is the purpose of valuation?
-
-
What are the factors considered while preparing the analysis of rates?Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2018
What are the factors affecting the Analysis of rates
-
-
Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.Long Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Find out the Dry Materials required for 1 cu.m Brick Masonry in Cement Mortar 1:5 in Foundation.
-
May 2022 Find dry materials required for 5m³ brick masonry in cement mortar 1:4.
-
May 2020 Find out the Dry Materials required for 1 cu.m Brick Masonry in Cement Mortar 1:5.
-
May 2018
Find out the dry material for 1cu.m brick masonry in cement sand mortar 1:4.
-
May 2017 Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
-
May 2015 Find out the dry material for 100 cu.m brick masonry in cement sand mortar 1:5.
-
Dec 2015 Find out dry material required for 1 cum. brick masonry in cement mortar 1:5.
-
-
Find out the dry material required for 1 cu.m cement concrete 1:2:4.Long Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Find out the Dry Materials required for 1 cu.m Cement Concrete 1:1.5:3.
-
May 2020 Find out the Dry Materials required for 1 cu.m Cement Concrete 1:2:4.
-
May 2018
Find out the dry material required for 1cu.m cement concrete 1:4:8
-
Dec 2018
Find out the Dry Materials required for 1 cu.m Cement Concrete 1:2:4
-
May 2017 Find out the dry material required for 1 cu.m cement concrete 1:2:4.
-
Dec 2017 Find out the dry material required for 10 cum cement concrete 1:2:4.
-
May 2015 Dry material required for 1 cu.m cement concrete is _________ cu.m.
-
May 2015 Find out the dry material required for 100 cu.m cement concrete 1:2:4.
-
-
Define tender. Write the name of various tender documents.Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Define Tender. Write the names of various Tender Documents.
-
May 2020 Define Tender. Write the names of various Tender Documents.
-
Dec 2018
Define Tender. Write the names of various Tender Documents.
-
Dec 2015 Write the name of various tender documents.
-
-
Define contractor. What are essential qualifications of a contractor?Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 What are the qualities and responsibilities of contractor?
-
May 2017 Define contractor. What are essential qualifications of a contractor?
-
May 2015 Define contractor. What are the essential qualifications of a contractor?
-
Dec 2015 What is contractor?
-
-
Write a short note on Scrap value and Earnest money.Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
Write a short note on different Measurement Books.Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
Write a short note on Depreciation and Muster Roll.Short Answer 6 Marks May-2019 • PSBTE DIPLOMA
-
May 2020 Write a short note on Depreciation of Buildings and different types of Building Estimates.
-
Dec 2018
Write a short note on Depreciation of Buildings and different types of Building Estimates.
-
May 2017 Write a short note on depreciation of buildings.
-
Dec 2017 Write a short note on depreciation.
-
May 2016 Write short note on Depreciation.
-
May 2015 Write a short note on depreciation of buildings.
-
-
Prepare a preliminary estimate of a building having plinth area equal to 2000 sq.m. Given that: Plinth area rate – Rs. 2500/- per sq.; Extra for Architectural work - 1½% of the building cost; Extra for Electrical Installation (10%) + Water supply and sanitary installations (6%) = 16% of the building cost; Extra for other services - 8% of the building cost; Contingencies and supervision charges 10%.Long Answer 10 Marks May-2019 • PSBTE DIPLOMA
-
May 2017 Prepare a preliminary estimate of a building having plinth area equal to 2000 sq.m. Given that plinth area rate is Rs. 2100/- per sq. m; extra for architectural work is 1.5% of the building cost; extra for electrical installation (10%) and water supply and sanitary installations (6%) = 16% of the building cost; extra for other services is 8% of the building cost; contingencies and supervision charges are 10%.
-
May 2015 Prepare a preliminary estimate of a building having plinth area equal to 1600 sq.m. Given that plinth area rate is Rs. 2000/- per sq.m; extra for architectural work is 1.5% of the building cost; extra for electrical installation (10%) plus water supply and sanitary installations (6%) = 16% of the building cost; extra for other services is 8% of the building cost; contingencies and supervision charges are 10%.
-
-
Work out the analyses of rates per cu.m for Brick work 1:4 cement sand mortar in superstructure. Labour for 10 cu.m brick work is 8 brick layers @ Rs. 350/- per day, 15 mazdor @ Rs. 200/-, 2 Bhisti @ Rs. 250/- per day. Rate of material: cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks = Rs. 3.5 per brick.Long Answer 10 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Prepare the Analysis of Rate for 1 cu.m of Brick Work 1:4 cement sand mortar in Superstructure, from the following data: Labour for 10 cu.m Mason: 8 no. @Rs. 350 per day; Labour: 15 no. @Rs. 200 per day; Water Man: 2 no. @ Rs. 250 per day; Cost of Material: Cement: Rs. 300 per Bag; Sand: Rs. 800 per cu.m; Bricks: Rs. 3.50 per brick.
-
May 2018
Workout the analyses of rates for brick masonry cement mortars 1:4 in superstructure. Labour for 10cu.m brick masonry 8 brick layer @ Rs. 500/- per day, 15 mazdor @ Rs. 300/- , 2 Bhisti @ Rs. 250/- per day. Rate of material: - cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks 4000/- per thousand.
-
-
Define an estimate. Give its importance or objectives. Name the various types of estimate.Long Answer 10 Marks May-2019 • PSBTE DIPLOMA
-
May 2017 Define an estimate. Give its importance or objectives. Name the various types of estimate.
-
May 2015 Define an estimate. Give its importance or objectives. Name the various types of estimate.
-
-
What is contract? Explain the different type of contract.Long Answer 10 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Explain different types of Contracts.
-
May 2022 What is meaning of Contract? Explain.
-
May 2020 Define Contract and explain it’s different types.
-
May 2018
Define Contract? What are the essential elements of contracts?
-
Dec 2018
Define Contract and explain its different types
-
May 2017 What is contract? Explain the different type of contract.
-
Dec 2017 What is contract? Explain different types of contract.
-
May 2015 What is contract? Explain the different types of contract.
-
Dec 2015 Define contract and explain different types of contracts.
-
May 2010 What is a contract? Explain its basic elements.
-
-
Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following data: Rd, N.S. level, Formation level: 0 - 205.00 - 210.00; 30 - 205.60 - ; 60 - 206.00 - ; 90 - 206.80 - ; The formation is in a downward gradient of 1 in 30. Formation width is 10 meters and side slope 2:1 (Horizontal: Vertical). Rate of earthwork is Rs. 400.00% cu.m.Long Answer 10 Marks May-2019 • PSBTE DIPLOMA
-
May 2017 Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following data: Rd 0, 30, 60, 90; N.S. levels 205.00, 205.60, 206.10, 206.90; formation in a downward gradient of 1 in 30; formation width 10 meters; side slope 2:1 (horizontal: vertical); rate of earthwork Rs. 425.00 per cu.m.
-
May 2015 Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following data: Rd 0 = 205.00, Rd 30 = 205.00, Rd 60 = 206.00, Rd 90 = 206.00, filling or banking level = 210.00. The formation is in a downward gradient of 1 in 30. Formation width is 10 meters and side slope is 2:1 (Horizontal:Vertical). Rate of earthwork is Rs. 400.00 per cu.m.
-
-
Work out the quantity of following items from the given drawing: a. Excavation for foundation b. Cement concrete 1:6:18 in foundation c. Mud Masonry in foundation and plinth d. Mud Masonry in super structureComprehension 10 Marks May-2019 • PSBTE DIPLOMA
-
May 2022 Work out the quantity of following items from the given drawing: a. Excavation for foundation b. Cement concrete 1:6:18 in foundation c. Brick masonry in cement mortar 1:7 in foundation and plinth d. Brick masonry in 1:5 super structures.
-
Dec 2017 Workout the quantities of the following items from the given drawing: (i) Earthwork in excavation. (ii) First class brick work in cement mortar in foundation and plinth. (iii) 2.5 cm cement concrete DPC. (iv) First class brick work in cement mortar 1:6 in super structure.
-
Explore all data
FAQ
Frequently Asked Questions
Answers about this subject, solved papers, and preparation.
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?
You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.
02 Is this page for Quantity Surveying and Valuation only?
Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.
03 Can I use these papers for revision before exams?
Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.
04 Are these official question papers from PSBTE?
No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.
05 Do you provide solved QSV question papers?
Some question papers may be available for practice, but this page does not guarantee solved papers for every year.