Solved question paper for QSV May-2020 (DIPLOMA 6th)
Solved Question Paper
Quantity surveying and valuation May-2020
PSBTE • DIPLOMA • Cvil Engineering • 6th • May-2020
QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.
Solved Questions
Solved-
Find out the Dry Materials required for 1 cu.m Brick Masonry in Cement Mortar 1:5.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 Find out the Dry Materials required for 1 cu.m Brick Masonry in Cement Mortar 1:5 in Foundation.
-
May 2022 Find dry materials required for 5m³ brick masonry in cement mortar 1:4.
-
May 2019 Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
-
May 2018
Find out the dry material for 1cu.m brick masonry in cement sand mortar 1:4.
-
May 2017 Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
-
May 2015 Find out the dry material for 100 cu.m brick masonry in cement sand mortar 1:5.
-
Dec 2015 Find out dry material required for 1 cum. brick masonry in cement mortar 1:5.
-
-
Find out the Dry Materials required for 10 sq.m Cement Plaster 1:4 (1.25 cm thick).Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
Dec 2018
Find out the Dry Materials required for 10 sq.m Cement Plaster 1:4 (1.25 cm thick).
-
Dec 2016 Find out the dry materials required for 10 sqm cement plaster 1:4 (1.25 cm thick).
-
-
Find out the Dry Materials required for 1 cu.m Cement Concrete 1:2:4.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 Find out the Dry Materials required for 1 cu.m Cement Concrete 1:1.5:3.
-
May 2019 Find out the dry material required for 1 cu.m cement concrete 1:2:4.
-
May 2018
Find out the dry material required for 1cu.m cement concrete 1:4:8
-
Dec 2018
Find out the Dry Materials required for 1 cu.m Cement Concrete 1:2:4
-
May 2017 Find out the dry material required for 1 cu.m cement concrete 1:2:4.
-
Dec 2017 Find out the dry material required for 10 cum cement concrete 1:2:4.
-
May 2015 Dry material required for 1 cu.m cement concrete is _________ cu.m.
-
May 2015 Find out the dry material required for 100 cu.m cement concrete 1:2:4.
-
-
What is Valuation? Write down the purpose of Valuation.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 What is Valuation? Write down the purpose of Valuation.
-
May 2019 What is valuation? Give the purpose of valuation.
-
May 2018
Define valuation. Give the purpose of valuation
-
Dec 2018
What is Valuation? Write down the purpose of Valuation.
-
May 2017 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
May 2016 Write short note on Purpose of valuation.
-
Dec 2016 What is valuation? Give the purpose of valuation.
-
May 2015 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
Dec 2015 What is valuation?
-
Dec 2015 Write down the purpose of valuation.
-
May 2010 Explain the purpose of valuation.
-
Dec 2008 Define valuation and explain purpose of valuation.
-
May 2007 What is the purpose of valuation?
-
-
Define Tender. Write the names of various Tender Documents.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 Define Tender. Write the names of various Tender Documents.
-
May 2019 Define tender. Write the name of various tender documents.
-
Dec 2018
Define Tender. Write the names of various Tender Documents.
-
Dec 2015 Write the name of various tender documents.
-
-
Write a short note on Depreciation of Buildings and different types of Building Estimates.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
May 2019 Write a short note on Depreciation and Muster Roll.
-
Dec 2018
Write a short note on Depreciation of Buildings and different types of Building Estimates.
-
May 2017 Write a short note on depreciation of buildings.
-
Dec 2017 Write a short note on depreciation.
-
May 2016 Write short note on Depreciation.
-
May 2015 Write a short note on depreciation of buildings.
-
-
Define the following terms: 1. Earnest Money 2. Administrative Approval.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
Dec 2018
Define the following terms:
\r\n\r\n1. Earnest Money 2. Administrative Approval.
-
-
Write a short note on Muster Role and Lump Sum Contract.Short Answer 5 Marks May-2020 • PSBTE DIPLOMA
-
Dec 2018
Write a short note on Muster Role and Lump Sum Contract
-
-
A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL are given below. If the Formation Level at RD 0 is 65.00 metre, estimate the quantity of cutting for the formation width of 10 m. The side slope is 2:1 and there is no cross-slope. Also find out the cost of cutting @ Rs. 450 per cu.m.Long Answer 10 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL are given below: R.D (m) 0, 30, 60, 90, 120, 150; NSL (m) 70.50, 69.30, 71.40, 74.00, 75.10, 73.50. If the Formation Level at RD 0 is 65.00 metre, estimate the Quantity of Cutting for the Formation Width of 10 m. The Side Slope is 2:1 and there is no cross-slope. Also find out the Cost of Cutting @ Rs. 450 per cu.m.
-
May 2022 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The natural surface levels are given below: R.D. 0 30 60 90 120 150; N.S. level 71.4 70.7 72.6 74.05 75.4 74. If the formation level at Rd 0 is 72.5 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1 (Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.500.00 per m³.
-
May 2018
A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30.The N.S levels are given below:
\r\n\r\n\r\n \r\n
\r\n\r\n\r\n \r\nRd \r\nN.S.(level) \r\n\r\n \r\n0 \r\n70.40 \r\n\r\n \r\n30 \r\n69.70 \r\n\r\n \r\n60 \r\n71.10 \r\n\r\n \r\n90 \r\n74.05 \r\n\r\n \r\n120 \r\n75.40 \r\n\r\n \r\n \r\n150 \r\n74.00 \r\nIf the formation level at Rd 0 is 65 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1(Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.450.00 cu m.
-
Dec 2018
SECTION-C
Attempt any three Questions. 10x3=30 Q4. A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL is given below:
R.D(m) NSL(m) 0 70.50 30 69.30 60 71.40 90 74.00 120 75.10 150 76.10 If the Formation Level at RD 0 is 75.00 metre, Estimate the Quantity of Cutting for the Formation Width of 10 m. The Side Slope is 2:1 and there is no cross-slope. Also find out the Cost of Cutting @ Rs. 450 % cu.m.
-
Dec 2016 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The N.S.L. are given below. If the formation level at Rd 0 is 75 meters, estimate the quantity of cutting for a formation width of 10 m. The side slope is 2:1 and there is no cross slope. Also find out the cost of cutting @450.00/cum.
-
Dec 2015 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The N.S. levels are given below: RD 0 = 70.50, 30 = 69.30, 60 = 71.40, 90 = 74.00, 120 = 75.10, 150 = 73.50. If the formation level at 0 is 65 m, estimate the quantity of cutting for a formation width of 10 metres. The side slope is 2:1 (Horizontal: Vertical) and there is no cross slope. Also find the cost of cutting @ Rs. 450 per cum.
-
-
Work out the quantities of the following items from the figure-1 of a Room: 4.0m x 3.60m (clear): i. Excavation for Foundation ii. P.C.C in Foundation (1:5:10) iii. Brick Masonry in Foundation and Plinth, laid in C.M. 1:5 iv. Brick Masonry in Superstructure, laid in C.M. 1:5Comprehension 10 Marks May-2020 • PSBTE DIPLOMA
-
Prepare the Analysis of Rate for 10 cu.m of Cement Concrete 1:2:4 from the following data: Labour for 10 cu.m Mason: 1 no. @ Rs. 300 per day; Labour: 15 no. @ Rs. 200 per day; Water Man: 2 no. @ Rs. 250 per day. Cost of Material Cement: Rs. 300 per Bag; Sand: Rs. 600 per cu.m; Bajri: Rs. 1200 per cu.m.Long Answer 10 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 Work out the analyses of rate for cement concrete 1:2:4 in slab. Labour for 10m³ cement concrete is 1 mason @ 450 Rs/day, 15 mazdoor @ 300 Rs/day, 2 Bhisti @ 200 Rs/day. Rate of material: cement bag Rs. 390/-, sand Rs. 850/- per m³. (Assume any missing data)
-
Dec 2018
Prepare the Analysis of Rate for 10 cu.m of Cement Concrete 1:2:4 from the following data:
\r\n\r\nLabour for 10 cu.m : Mason: 1 no. @Rs. 300 per day
\r\n\r\nLabour: 15 no. @Rs. 200 per day
\r\n\r\nWater Man: 2 no. @ Rs. 250 per day
\r\n\r\nCost of Material Cement: Rs. 300 per Bag
\r\n\r\nSand: Rs. 600 per cu.m
\r\n\r\nBajri: Rs. 1200 per cu.m.
-
May 2017 Work out the analyses of rates for cement concrete 1:4:8 in foundation. Labour for 10 cu.m cement concrete is 1 mason @ Rs. 450/- per day, 15 mazdoor @ Rs. 250/- per day, 2 bhisti @ Rs. 200/- per day. Rate of material: cement bag Rs. 300/-, sand Rs. 800/- per cu.m, coarse aggregate (bazri) Rs. 1000/- per cu.m.
-
May 2016 Prepare the analysis of rate for 10 cum of cement concrete 1:2:4 from the given data: labour for 10 cum; Mason = 1 @ Rs. 300 per day, Labour = 15 @ Rs. 200 per day, Water man = 2 @ Rs. 250 per day. Cost of material: Cement = Rs. 300 per bag, Sand = Rs. 600 per cum, Bajri = Rs. 1200 per cum.
-
Dec 2016 Work out the analyses of rate for cement concrete 1:2:4 in slab. Labour for 10 cum cement concrete is 1 mason @ 450 Rs/day, 15 mazdoor @ 300 Rs/day, 2 bhisti @ 200 Rs/day. (Assume any other required data).
-
May 2015 Work out the analysis of rates for cement concrete 1:4:8 in foundation. Labour for 10 cu.m cement concrete is 1 mason @ Rs. 500/- per day, 15 mazdor @ Rs. 300/- per day, 2 bhisti @ Rs. 250/- per day. Rate of material: cement bag Rs. 250/-, sand Rs. 600/- per cu.m, course aggregate (bazri) Rs. 1000/- per cu.m.
-
-
Define Contract and explain it’s different types.Short Answer 10 Marks May-2020 • PSBTE DIPLOMA
-
May 2022 Explain different types of Contracts.
-
May 2022 What is meaning of Contract? Explain.
-
May 2019 What is contract? Explain the different type of contract.
-
May 2018
Define Contract? What are the essential elements of contracts?
-
Dec 2018
Define Contract and explain its different types
-
May 2017 What is contract? Explain the different type of contract.
-
Dec 2017 What is contract? Explain different types of contract.
-
May 2015 What is contract? Explain the different types of contract.
-
Dec 2015 Define contract and explain different types of contracts.
-
May 2010 What is a contract? Explain its basic elements.
-
-
Define the following terms: i. Sinking Fund ii. Scrap Value iii. Capital Cost iv. Gross Income v. Year Purchase.Short Answer 10 Marks May-2020 • PSBTE DIPLOMA
-
Dec 2018
Explain the following terms:
\r\n\r\na. Sinking Fund
\r\n\r\nb. Scrap Value
\r\n\r\nc. Capital Cost
\r\n\r\nd. Gross Income
\r\n\r\ne. Year Purchase
-
Explore all data
FAQ
Frequently Asked Questions
Answers about this subject, solved papers, and preparation.
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?
You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.
02 Is this page for Quantity Surveying and Valuation only?
Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.
03 Can I use these papers for revision before exams?
Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.
04 Are these official question papers from PSBTE?
No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.
05 Do you provide solved QSV question papers?
Some question papers may be available for practice, but this page does not guarantee solved papers for every year.