QSV (Quantity Surveying and Valuation) for Punjab State Board of Technical Education Diploma in Engineering Civil Engineering 6th semester helps students find subject-wise previous year question papers, old papers, and exam preparation material. These papers are useful for revision, understanding the exam pattern, and spotting repeated question styles before the exam. BRpaper is not the official website of the Punjab State Board of Technical Education or any board or university. Use this page to explore QSV question paper PDFs and old exam papers for better practice and preparation.
Solved Questions
Solved-
How many bricks are required for 1 cu.m Brick Masonry?Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2019 Number of bricks required for 1 Cu.m brick masonry is ______.
-
Dec 2018
Fill in the blanks.
\r\n\r\ni. No. of bricks for 1 cu.m Brick Masonry is ________.
-
May 2017 Number of bricks required for 1 cu.m brick masonry is __________.
-
Dec 2017 No. of bricks in 1 cum of brick masonry is __________
-
May 2015 Number of bricks required for 1 cu.m brick masonry is _________.
-
Dec 2015 Number of bricks required for 1 cum. brick masonry is __________.
-
-
What is the use of Muster Roll?Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
What is the %age of Contractor’s Profit that must be added to obtain the rate per unit of item of work?Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
How much quantity of dry mortar is required for 1 cu.m of Cement Concrete?Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 Total Dry material required for 1m³ cement concrete is ________ m³.
-
May 2019 Total dry material required for 1 cu.m cement concrete is _____ cu.m.
-
Dec 2017 Dry material required for 1 cum of cement concrete is __________ cum
-
Dec 2015 Dry mortar required for 1 cum cement concrete is __________.
-
-
Define Depriciation.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
What do you understand by M.B?Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
What is the use of Bar Bending Schedule?Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
Define Salvage Value.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 Explain Scrap Value.
-
Dec 2016 Define scrap value.
-
May 2010 Discuss scrap value.
-
-
Define Book Value.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
Give the duties of Quantity Surveyor.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 What are the duties of Quantity Surveyor?
-
Dec 2008 Write the main duties of quantity surveyor.
-
-
State the Units of Measurement for Brick work.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 State the unit of measurement for Brick Work.
-
May 2019 State the unit of measurement for Brick Work.
-
Dec 2017 State the units of measurement for brick work in foundation.
-
Dec 2017 State the units of measurement for ashlar masonry.
-
Dec 2016 State the Units of Measurement of brick work.
-
Dec 2015 State the units of measurements for brick work.
-
May 2007 Give the unit of measurement for honey comb brick work.
-
-
State the Units of Measurement for Flooring.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2019 State the unit of measurement for Flooring.
-
May 2017 State the unit of measurement for flooring.
-
Dec 2017 State the units of measurement for concrete flooring.
-
May 2016 State the units of measurements and payment for Flooring.
-
Dec 2015 State the units of measurements for flooring.
-
-
State the Units of Measurement for Earthwork.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2019 State the unit of measurement for Earthwork.
-
Dec 2017 State the units of measurement for earthwork.
-
May 2016 State the units of measurements and payment for Earthwork.
-
May 2015 State the unit of measurement for Earthwork.
-
Dec 2015 State the units of measurements for earth work.
-
-
State the Units of Measurement for Skirting.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2019 State the unit of measurement for Skirting.
-
Dec 2016 State the Units of Measurement of skirting.
-
-
State the Units of Measurement for Cement Plaster.Very Short Answer 1 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 State the unit of measurement for Cement Plaster.
-
May 2022 State the unit of measurement for Cement Plaster.
-
Dec 2017 State the units of measurement for cement concrete.
-
Dec 2016 State the Units of Measurement of lime concrete.
-
Dec 2015 State the units of measurements for cement concrete.
-
Dec 2015 State the units of measurements for cement plaster.
-
Dec 2015 Units of payment for cement concrete is ___________.
-
Dec 2008 Write the units of measurement and payment for precast cement concrete.
-
-
What do you understand by Specifications of Works?Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2017 What do you understand by specification of works?
-
-
Write a short note on different types of Building Estimates.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
Find out the Dry Materials required for 1 cu.m Brick Masonry in Cement Mortar 1:5 in Foundation.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 Find dry materials required for 5m³ brick masonry in cement mortar 1:4.
-
May 2020 Find out the Dry Materials required for 1 cu.m Brick Masonry in Cement Mortar 1:5.
-
May 2019 Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
-
May 2018
Find out the dry material for 1cu.m brick masonry in cement sand mortar 1:4.
-
May 2017 Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
-
May 2015 Find out the dry material for 100 cu.m brick masonry in cement sand mortar 1:5.
-
Dec 2015 Find out dry material required for 1 cum. brick masonry in cement mortar 1:5.
-
-
Find out the Dry Materials required for 1 cu.m Cement Concrete 1:1.5:3.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
May 2020 Find out the Dry Materials required for 1 cu.m Cement Concrete 1:2:4.
-
May 2019 Find out the dry material required for 1 cu.m cement concrete 1:2:4.
-
May 2018
Find out the dry material required for 1cu.m cement concrete 1:4:8
-
Dec 2018
Find out the Dry Materials required for 1 cu.m Cement Concrete 1:2:4
-
May 2017 Find out the dry material required for 1 cu.m cement concrete 1:2:4.
-
Dec 2017 Find out the dry material required for 10 cum cement concrete 1:2:4.
-
May 2015 Dry material required for 1 cu.m cement concrete is _________ cu.m.
-
May 2015 Find out the dry material required for 100 cu.m cement concrete 1:2:4.
-
-
Give the Qualities of a good Contractor.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2015 Write the qualification of a good contractor.
-
-
What is Valuation? Write down the purpose of Valuation.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
May 2020 What is Valuation? Write down the purpose of Valuation.
-
May 2019 What is valuation? Give the purpose of valuation.
-
May 2018
Define valuation. Give the purpose of valuation
-
Dec 2018
What is Valuation? Write down the purpose of Valuation.
-
May 2017 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
May 2016 Write short note on Purpose of valuation.
-
Dec 2016 What is valuation? Give the purpose of valuation.
-
May 2015 Define valuation. Give the purpose of valuation. State and explain the various methods of valuation.
-
Dec 2015 What is valuation?
-
Dec 2015 Write down the purpose of valuation.
-
May 2010 Explain the purpose of valuation.
-
Dec 2008 Define valuation and explain purpose of valuation.
-
May 2007 What is the purpose of valuation?
-
-
Define Tender. Write the names of various Tender Documents.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
May 2020 Define Tender. Write the names of various Tender Documents.
-
May 2019 Define tender. Write the name of various tender documents.
-
Dec 2018
Define Tender. Write the names of various Tender Documents.
-
Dec 2015 Write the name of various tender documents.
-
-
Define Earnest Money.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2008 Explain in brief: Earnest money.
-
-
Define Administrative Approval.Short Answer 5 Marks May-2022 • PSBTE DIPLOMA
-
A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL are given below: R.D (m) 0, 30, 60, 90, 120, 150; NSL (m) 70.50, 69.30, 71.40, 74.00, 75.10, 73.50. If the Formation Level at RD 0 is 65.00 metre, estimate the Quantity of Cutting for the Formation Width of 10 m. The Side Slope is 2:1 and there is no cross-slope. Also find out the Cost of Cutting @ Rs. 450 per cu.m.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The natural surface levels are given below: R.D. 0 30 60 90 120 150; N.S. level 71.4 70.7 72.6 74.05 75.4 74. If the formation level at Rd 0 is 72.5 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1 (Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.500.00 per m³.
-
May 2020 A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL are given below. If the Formation Level at RD 0 is 65.00 metre, estimate the quantity of cutting for the formation width of 10 m. The side slope is 2:1 and there is no cross-slope. Also find out the cost of cutting @ Rs. 450 per cu.m.
-
May 2018
A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30.The N.S levels are given below:
\r\n\r\n\r\n \r\n
\r\n\r\n\r\n \r\nRd \r\nN.S.(level) \r\n\r\n \r\n0 \r\n70.40 \r\n\r\n \r\n30 \r\n69.70 \r\n\r\n \r\n60 \r\n71.10 \r\n\r\n \r\n90 \r\n74.05 \r\n\r\n \r\n120 \r\n75.40 \r\n\r\n \r\n \r\n150 \r\n74.00 \r\nIf the formation level at Rd 0 is 65 meters, estimate the quantity of cutting for a formation width of 10 meters. The side slope is 2:1(Horizontal: vertical) and there is no cross slope. Also find out the cost of cutting @ Rs.450.00 cu m.
-
Dec 2018
SECTION-C
Attempt any three Questions. 10x3=30 Q4. A short Link Road to be constructed entirely in Cutting at a uniform rising gradient 1 in 30, the NSL is given below:
R.D(m) NSL(m) 0 70.50 30 69.30 60 71.40 90 74.00 120 75.10 150 76.10 If the Formation Level at RD 0 is 75.00 metre, Estimate the Quantity of Cutting for the Formation Width of 10 m. The Side Slope is 2:1 and there is no cross-slope. Also find out the Cost of Cutting @ Rs. 450 % cu.m.
-
Dec 2016 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The N.S.L. are given below. If the formation level at Rd 0 is 75 meters, estimate the quantity of cutting for a formation width of 10 m. The side slope is 2:1 and there is no cross slope. Also find out the cost of cutting @450.00/cum.
-
Dec 2015 A short link road is to be constructed entirely in cutting at a uniform rising gradient 1 in 30. The N.S. levels are given below: RD 0 = 70.50, 30 = 69.30, 60 = 71.40, 90 = 74.00, 120 = 75.10, 150 = 73.50. If the formation level at 0 is 65 m, estimate the quantity of cutting for a formation width of 10 metres. The side slope is 2:1 (Horizontal: Vertical) and there is no cross slope. Also find the cost of cutting @ Rs. 450 per cum.
-
-
Work out the Quantities of Excavation for Foundation from the given Drawing (Wall thickness-0.30 m all around).Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2017 Work out the quantity of excavation for foundation from the given drawing.
-
May 2016 Calculate the quantities of excavation for foundation from the sketch attached.
-
Dec 2016 Work out the quantities of excavation for foundation from the given drawing.
-
May 2015 Work out the quantity of excavation for foundation from the given drawing.
-
-
Work out the Quantities of P.C.C in Foundation (1:6:18) from the given Drawing (Wall thickness-0.30 m all around).Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2017 Work out the quantity of cement concrete 1:6:18 in foundation from the given drawing.
-
Dec 2016 Work out the quantities of cement concrete 1:6:18 in foundation from the given drawing.
-
May 2015 Work out the quantity of cement concrete 1:6:18 in foundation from the given drawing.
-
-
Work out the Quantities of Mud Masonry in Foundation and Plinth from the given Drawing (Wall thickness-0.30 m all around).Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2017 Work out the quantity of mud masonry in foundation and plinth from the given drawing.
-
Dec 2016 Work out the quantities of brick masonry in foundation and plinth from the given drawing.
-
May 2015 Work out the quantity of mud masonry in foundation and plinth from the given drawing.
-
Dec 2008 Work out the quantities of excavation for foundation for a room as shown in Figure 1.
-
Dec 2008 Work out the quantities of lime concrete in foundation for a room as shown in Figure 1.
-
Dec 2008 Work out the quantities of mud masonry in foundation and plinth for a room as shown in Figure 1.
-
Dec 2008 Work out the quantities of mud masonry in super structure for a room as shown in Figure 1.
-
May 2007 Work out quantities of excavation for foundation for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
May 2007 Work out quantities of CC in foundation for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
May 2007 Work out quantities of brick work in foundation and plinth in cement mortar for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
May 2007 Work out quantities of brick work in super structure in cement mortar for a two roomed quarter as per drawing given in figure-1 (overleaf).
-
-
Work out the Quantities of Mud Masonry in Superstructure from the given Drawing (Wall thickness-0.30 m all around).Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2017 Work out the quantity of mud masonry in super structure from the given drawing.
-
May 2015 Work out the quantity of mud masonry in super structure from the given drawing.
-
-
Prepare the Analysis of Rate for 1 cu.m of Brick Work 1:4 cement sand mortar in Superstructure, from the following data: Labour for 10 cu.m Mason: 8 no. @Rs. 350 per day; Labour: 15 no. @Rs. 200 per day; Water Man: 2 no. @ Rs. 250 per day; Cost of Material: Cement: Rs. 300 per Bag; Sand: Rs. 800 per cu.m; Bricks: Rs. 3.50 per brick.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2019 Work out the analyses of rates per cu.m for Brick work 1:4 cement sand mortar in superstructure. Labour for 10 cu.m brick work is 8 brick layers @ Rs. 350/- per day, 15 mazdor @ Rs. 200/-, 2 Bhisti @ Rs. 250/- per day. Rate of material: cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks = Rs. 3.5 per brick.
-
May 2018
Workout the analyses of rates for brick masonry cement mortars 1:4 in superstructure. Labour for 10cu.m brick masonry 8 brick layer @ Rs. 500/- per day, 15 mazdor @ Rs. 300/- , 2 Bhisti @ Rs. 250/- per day. Rate of material: - cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks 4000/- per thousand.
-
-
Explain different types of Contracts.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 What is meaning of Contract? Explain.
-
May 2020 Define Contract and explain it’s different types.
-
May 2019 What is contract? Explain the different type of contract.
-
May 2018
Define Contract? What are the essential elements of contracts?
-
Dec 2018
Define Contract and explain its different types
-
May 2017 What is contract? Explain the different type of contract.
-
Dec 2017 What is contract? Explain different types of contract.
-
May 2015 What is contract? Explain the different types of contract.
-
Dec 2015 Define contract and explain different types of contracts.
-
May 2010 What is a contract? Explain its basic elements.
-
-
Explain Sinking Fund.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2016 Define sinking fund.
-
-
Explain Scrap Value.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
May 2022 Define Salvage Value.
-
Dec 2016 Define scrap value.
-
May 2010 Discuss scrap value.
-
-
Explain Capital Cost.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2016 Define capital cost.
-
-
Explain Gross Income.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2016 Define gross income.
-
-
Explain Year Purchase.Long Answer 10 Marks May-2022 • PSBTE DIPLOMA
-
Dec 2016 Define year purchase.
-
Explore all data
FAQ
Frequently Asked Questions
Answers about this subject, solved papers, and preparation.
01 Where can I find QSV previous year question papers for Civil Engineering 6th semester?
You can use this page to look for QSV old question papers and previous year papers for PSBTE Diploma in Civil Engineering 6th semester.
02 Is this page for Quantity Surveying and Valuation only?
Yes, this page is focused on QSV, which stands for Quantity Surveying and Valuation, for the 6th semester Civil Engineering course.
03 Can I use these papers for revision before exams?
Yes, previous year papers are helpful for revision, practicing questions, and understanding the exam pattern for QSV.
04 Are these official question papers from PSBTE?
No, BRpaper is not the official website of Punjab State Board of Technical Education. It only helps students find previous year papers and related study material.
05 Do you provide solved QSV question papers?
Some question papers may be available for practice, but this page does not guarantee solved papers for every year.