Previous Year Very Short Questions of IE (DIPLOMA Production and Industrial Engineering 5th)

Industrial Engineering

Previous year question paper with solutions for Industrial Engineering

Our website provides solved previous year question paper for Industrial Engineering . Doing preparation from the previous year question paper helps you to get good marks in exams. From our IE question paper bank, students can download solved previous year question paper. The solutions to these previous year question paper are very easy to understand.

These Questions are downloaded from www.brpaper.com You can also download previous years question papers of 10th and 12th (PSEB & CBSE), B-Tech, Diploma, BBA, BCA, MBA, MCA, M-Tech, PGDCA, B-Com, BSc-IT, MSC-IT.

Print this page
  1. Technique used for doing things in better way is called __________.
  2. The standard time for a job is normal time + __________
  3. Process layout is employed for _____________ production.
  4. Gnatt charts are used for ____________.
  5. The method used for finding relative value of a job is called __________.
  6. ‘O’ is method study symbol used to represent _____________.
  7. The basic work measurement tool is ______________
  8. _________ Schemes are intended to increase workers motivation by allowing them to earn proportionately higher from their greater efforts.
  9. Conveyers are useful when material moves ___________
  10. _________ is the measure of how well the resources are brought together in an organization and utilized for accomplishing a set of objectives.
  11. Gantt chart is used for production Schedule.
  12. The objective of scientific layout is to utilize max floor area.
  13. Method study is done for calculating standard time.
  14. In an outline process chart all the symbols are used.
  15. Line or product type layout is useful in mass production.
  16. Production and productivity are same thing.
  17. In piece rate system no consideration is given to time taken by a worker.
  18. Workers generally oppose work study.
  19. O is a symbol for storage.
  20. According to motion economy, both hands should not start and finish the work simultaneously.
  21. Method study and Work Measurement are called ……………….
  22. Production is converting …………………. Into…………………………
  23. Productivity Index = ………………………
  24. ∆ Symbol in work study implies …………………….
  25. String diagram is used for …………………………….
  26. Therbligs were suggested by ………………………
  27. Motion picture camera is used for recording ……………………
  28. Relaxation allowance is given for …………………………
  29. Standard time= …………………….. + Allowances.
  30. …………….. is an reward monetary/non-monetary given to a worker for his hard work.